Hi Dharmesh,
Alternate resource is not supported by PDS. But still if you have maintained alternate resource in routing then, it will come as alternate modes in PDS but capacity will not be distributed.
You have to create multiple PDS out of alternate resource for which few enhancement need to be done in CIF.
Not possible in standard SAP.
regards
Kishor