Hi Experts,
I am trying to create a WBS element under a proj definition using BAPI_PROJECT_MAINTAIN. I get error as : Fill in all the required fields.
I have filled I_PROJECT_DEFINITION with,
PROJECT_DEFINITION , DESCRIPTION , BUS_AREA.
I_METHOD_PROJECT WITH,
REFNUM OBJECTTYPE METHOD OBJECTKEY
0000001 WBS-ELEMENT CREATE "SOME VALUE
0000000 SAVE
I_WBS_ELEMENT_TABLE WITH,
WBS_ELEMENT PROJECT_DEFINITION DESCRIPTION BUS_AREA.
And when executed in SE37, I get error Fill in all the required fields.E055(00).
I have googled for missing field. Some said, to keep PROFIT_CTR as DUmmy.But when I do this I get : profit center 0010/dummy doesnt exist.
Any pointer, please help.
Thanks,
Anil