We have two different processes how the activity of the same cost centre will be allocated to the receiver objects:

 

with activity type B: all acitivities related to major projects (internal orders) with a pre-defined, fixed tarif (valid for all cost centres charging activities on these projects)

 

with activity type A: all remaining activities related to maintenance on equipement with work orders (SAP-PM) with a calculated tarif based on total costs (incl.settlement of act.type B) and activities planned on work orders

 

hope this helps.

kind regards,

 