Re: Is there any way to transfer the Start date of Pur Requisition from APO (RRP3 screen) to ECC ME23N?

$
0
0

I think you are mistaken.

 

THe Opening date is CIF'd to ECC release date and is not changed.

 

Opening Date = APO End Date - APO GR Time (Receiving Calendar) - Max(Transportation Lane  Duration, APO Planned Delivery Time) - APO GI Time (Shipping Calendar) - APO Opening Period (Shipping Calendar)   

 

So your planned delivery time is too large.   Why have a transportation duration so small.

 

In fact you should set the planned delivery time to zero in APO if you have a transportation lane into that location.

 

Ken