Re: How do we automatically transfer cost across WBSEs given the scenario below?

$
0
0

Hi Ken,

 

1.  We are using a non- valuated project stock.

2. No we are not, but we can.  Current process is we issue the PO with one line for the whole order (using account assigment category P) then the puchasing controller amends the PO by itemising the order and relating them to a material code using account assignment Category Q

3. They are stored as plant stock.